PAGE THIRTY-SIX 1177TH HISTORY
B.S.I., FROM 1 SEPTEMBER 1944 TO 20 APRIL 1945, PER GENERAL
ORDER 40, HQS ISLAND COMMAND, APO 709, DATED 22 APRIL 1945.
THE FOLLOWING PROJECTS WERE STARTED:
2ND - RUSSELL ISLAND HUTS RECRATING BY 1393RD ECB
3RD - MOVE AND RELOCATE MARINE FIREHOUSE BY 1393RD ECB
- CLEARING OF DRAINAGE COURSES BY 1394TH ECB
- DISMANTLING NEW ZEALAND RADAR, GUADALCANAL, BY 1393RD
ECB
4TH - GRAVELING TENARU GAS DUMP BY 1394TH ECB
- ROAD REPAIR POINT CRUZ AMMUNITION DUMP #3 BY 1393RD
ECB
5TH - SHIFT OF MESS HALL AT REST CAMP BY 1394TH ECB
- DECK PATCHING AT POINT CRUZ PIER BY 1393RD ECB
6TH - CONSTRUCTION OF SHOWER HOUSE, 9TH STATION HOSPITAL,
BY 1394TH ECB
7TH - CONSTRUCTION OF LIBERTY SHIP TROOP FACILITIES BY
1393RD ECB
- METALS DUMP ACCESS ROAD BY 1393RD ECB
8TH - ELECTRIC SYSTEM AT ORDNANCE DEPOT BY 1393RD ECB
11TH - CONSTRUCTION OF ELEVATED WATER STORAGE TANKS, CAMP
GUADAL, BY 1394TH ECB
- SALVAGE OF 568TH ENGINEER DUMP TRUCK COMPANY CAMP BY
1393RD ECB
12TH - CONSTRUCTION OF ADDITIONAL GENERATOR FACILITIES AT
REST CAMP BY 1394TH ECB
THE FOLLOWING PROJECTS WERE COMPLETED:
3RD - CLEARING OF DRAINAGE COURSES
4TH - SALVAGE OF KOLI QUARTERMASTER CAMP
5TH - TENARU GAS DUMP GRAVELING
- SALVAGE OF 456TH AMPHIBIOUS TRACTOR AREA
6TH - DECK PATCHING POINT CRUZ PIER